Roof Penetrations

Large Penetrations


  • When a penetration is 15 m or less from the highest point of the roof, a soaker tray is the preferred option to be installed to the termination.
  • Large penetrations that exceed the pan width must be provided with additional structural framing to all four sides.
  • Wherever one or more of the sheet ribs are cut, framing must be provided to support the cut ends of the roof cladding each side of the penetration.

Small Penetrations


Penetrations through metal roofs must:

  • Be positioned at or near the high point whenever practicable
  • Have “Dektites” fitted on a tray
  • Incorporate a shepherd’s crooks where suitable (refer figure below).
  • Only have smooth-walled conduit (flexible conduit is not permitted under any circumstances).
  • Incorporate EPDM rubber grommets for copper pipe penetrations
  • If a copper pipe, it must be painted over the entire exposed length
  • Incorporate a shepherd’s crooks where suitable (refer figure below).
  • Incorporate Red Dektites flues where heat resistant is required.

Document Control


Version 2.1, April 2021