Natural Gas
Materials
Gas pipework must be:
- Metal from the authority meter location to the entry to the building and in risers and branch lines
- As per approved sample throughout the building.
Below Ground Clearances
Separation between other services must be in accordance in with 'Below Ground Separation Distances'.
Below Ground Backfill and Cover
- Cover must be not less than that given in the Table outlined below.
- Metal gas pipes which are permitted to be used in the ground for gas in accordance with Table 4.1 of AS 5601.1:2013 must be:
- Coated or covered with a proprietary wrapping.
- Installed with underground pipe warning tape and trace wire 150mm above all underground pipes for the full length of the pipe.
Above Ground Clearances
- Separation between other services must be in accordance with 'Above Ground Separation Distances'.
Casting into Concrete
- Copper pipes must not be embedded or cast into concrete structures
- PEX pipes embedded in a concrete must be:
- Installed in an approved conduit.
- Installed with no joints in the pipe.
Brackets and Supports
- Gas pipes must be supported at spacing in accordance with 'Horizontal Pipe Support Spacing' and 'Vertical Pipe Support Spacing'.
- Diameter of rod hangers must comply with the Figure 9.
Piping in an air duct, plenum ceiling, air handling plenum or ventilating duct
- Consumer piping as per Clause 4.10.17 of AS5601 in an air duct, air plenum ceiling, air handling plenum or ventilating duct must:
- Have an operating pressure not exceeding 7 kPa
- Keep number of joints to the minimum
- Have all permanent joints.
Gas Piping in Concealed Locations
- Gas piping in concealed locations must be in accordance with Table 4.6 of AS 5601 outlined below:
Testing
- Pressure test the gas pipework to 3 times the working pressure with compressed air for 5 minutes.