Click herefor instructions on How to Print a Web Page
Completion and Handover
The Subcontractor/s must provide a full operational demonstration to the client or client's agent before handover and include a thorough introduction to all elements of the:
Pool equipment
Pool water
Pool area
Health and safety requirements.
The Operation and Maintenance Manual must be available for familiarisation and any questions should be fully explained and in writing if required.
Before any handover is attempted all goods and services, maintenance equipment and water treatment chemicals required by the Contract must be delivered to site and where appropriate, installed and working.
The subcontractor must then provide such oral and written instruction as may be necessary to ensure that the client or the client's agent understands all aspects of the operation of the pool and its associated equipment and chemical dosing system.
Written instructions must be in a coherent form specially drafted and appropriate for the complete installation in question.
The contractor must also supply to the Client required safety information for inclusion in the Project Safety File. This information should include:
A risk assessment,
Safe Work Method Statements or Standard Operation Procedures as appropriate
Material data sheets.
A pool water circulation dye test to be considered being carried out at the commissioning stage of the swimming pool.