ITP’s, Checklists and Traceability Records (get an example shop drawing with ITP)
- The Inspection and Test Plan (ITP) must be developed by the precast manufacturer and issued to Multiplex for acceptance prior to works commencing.
- For each precast element, an inspection checklist must be produced and the current shop drawing attached to show evidence of inspection / verification prior to pouring of the concrete.
- Verification records as a minimum must include:
- Form / mould measurement verification
- Concrete strength
- Reinforcement (size / number / placement)
- Grout tubes and bleed tubes that are checked and clear
- Cast-in elements (size / number / placement)
- Specified finish.
Traceability of Precast Concrete Units
- Each individual precast element must have a unique identification number recorded on the element along with the weight and cast date.
- This information must also be recorded on the birth certificate.
Pre-pour Inspection
Before a concrete element is cast, the form arrangement and set up must be inspected by a competent person for compliance verified against the shop drawings.
- The competent person needs to be familiar with the construction of the concrete element and must be able to accurately read and understand the relevant, approved shop drawings.
- All structural precast must be inspected by the project Structural Engineer, accompanied by a Multiplex representative, at the following hold points:
1.Prior to casting the first batch
2.Monthly until completion of all elements.