Commissioning and Handover

Building works items that need to be completed in some cases several months ahead of PC to enable the commissioning and handover of the building include:

  • Plant rooms and plant areas completed.
  • Façade complete and air tight.
  • Building air shafts complete and air tight.
  • Fire and smoke compartments sealed which includes façade, walls (full height), doors and hardware installed.
  • Doors with access control to have all hardware installed.
  • Fire stairs complete including doors, hardware and closers installed.
  • Fire control room and fire pump room complete and clean.
  • Boundary Trap Rooms/ Gas Meter Rooms/ Hydraulic Pump rooms painted, clean.
  • Electrical rooms and cupboards clean and lockable.
  • Communications rooms /cupboards painted, clean and lockable.
  • BMCS room /cupboards painted, clean and lockable.
  • Lights installed to test lighting control.
  • Ceiling and all flooring (majority) installed to check lux levels (normal lights and emergency lights).