Building works items that need to be completed in some cases several months ahead of PC to enable the commissioning and handover of the building include:
- Plant rooms and plant areas completed.
- Façade complete and air tight.
- Building air shafts complete and air tight.
- Fire and smoke compartments sealed which includes façade, walls (full height), doors and hardware installed.
- Doors with access control to have all hardware installed.
- Fire stairs complete including doors, hardware and closers installed.
- Fire control room and fire pump room complete and clean.
- Boundary Trap Rooms/ Gas Meter Rooms/ Hydraulic Pump rooms painted, clean.
- Electrical rooms and cupboards clean and lockable.
- Communications rooms /cupboards painted, clean and lockable.
- BMCS room /cupboards painted, clean and lockable.
- Lights installed to test lighting control.
- Ceiling and all flooring (majority) installed to check lux levels (normal lights and emergency lights).